Transferring an Estimate to Budget Manager
You can transfer an estimate created in Preconstruction into the Budget Manager tool for ongoing project cost tracking.
Step 1: Navigate to the Estimate
- Open the project where the estimate is located.
- In the project tabs, click Preconstruction → Estimate.
- Open the estimate you want to transfer.
Step 2: Export to Budget
- In the top-right corner, click Export.
- Select Export to Project Budget.
Step 3: Configure Export Options
- You’ll see an option to include markups:
- If checked, the total amounts transferred to the budget will be inclusive of markups.
- If unchecked, only base amounts will be transferred.
Step 4: Finalize Export
- Click Export to Budget to complete the transfer.
- The system will create all entries in the Budget Manager based on the estimate.
Important Notes
- If the estimate has been previously exported to Budget Manager, the system will compare each entry against existing budget entries.
- A match is determined by the exact combination of:
- Job
- Cost Code
- Cost Type
- Description
- Unit
- Quantity
- Unit Cost
- If an entry with this combination already exists in Budget Manager, it will be ignored during export and not recreated.
- This process prevents duplicate entries and keeps your budget data accurate and consistent.