Understanding the CSI Format for Construction Specifications

In construction, clear communication is everything. One of the most widely used tools for standardizing project documentation is the Construction Specifications Institute (CSI) format. The CSI, through its MasterFormat system, provides a standardized structure for organizing specifications, cost data, and project information.

What is the CSI Format?

The CSI format is essentially a classification system that organizes construction specifications into Divisions, Sections, and Parts. This system ensures that everyone—from architects and engineers to contractors and suppliers—uses the same language when referring to materials, systems, and requirements.

The CSI MasterFormat currently contains 50 divisions covering every aspect of construction, from general requirements to electrical systems and finishes. Within each division, specifications are broken down into sections, and each section typically follows a three-part format:

  1. Part 1 – General: Describes administrative requirements, references, submittals, quality assurance, and project conditions.
  2. Part 2 – Products: Defines materials, products, equipment, and standards required.
  3. Part 3 – Execution: Explains installation methods, workmanship, testing, and cleanup.

Example: Division 09 – Finishes, Section 09 29 00 – Gypsum Board

Here’s how a sample section might look using CSI formatting:

09 29 00 – Gypsum Board

Part 1 – General

1.1 References

A. ASTM C1396 – Standard Specification for Gypsum Board

B. ASTM C840 – Application and Finishing of Gypsum Board

1.2 Submittals

A. Product data for gypsum board, joint treatment, and fasteners

B. Samples: One 12x12-inch piece of each board type

1.3 Delivery, Storage, and Handling

A. Deliver in manufacturer’s packaging with labels intact

B. Store flat in dry, well-ventilated conditions


Part 2 – Products

2.1 Gypsum Board

A. Type: 5/8-inch Type X, ASTM C1396 compliant

B. Manufacturer: [Approved Manufacturer List]

2.2 Joint Treatment

A. Ready-mix joint compound, ASTM C475 compliant

B. Paper tape for joints

2.3 Fasteners

A. Type S screws for attaching board to metal studs

B. Corrosion-resistant finish


Part 3 – Execution

3.1 Installation

A. Install gypsum board per ASTM C840 and manufacturer’s instructions

B. Orient boards perpendicular to framing members

3.2 Finishing

A. Apply joint treatment in three coats

B. Sand between coats to achieve smooth, Level 4 finish

3.3 Cleaning

A. Remove dust and debris from work area

B. Dispose of scrap material off-site

Why CSI Format Matters

Using the CSI format improves clarity, efficiency, and consistency across project teams. It reduces misunderstandings, helps contractors price work more accurately, and provides a roadmap for quality construction practices.

By organizing specifications in this way, projects run smoother, and everyone has a shared reference point for expectations.